Alex requested 3 quotes from Concreters in Algester
I have full drawings available however this site will not let me attach them,
Size – Total of 47.5m2
Formwork – Total of 18.4 m of formwork is required. The rest of the areas area against existing concrete walls.
Prep is completed down to dirt at approx the correct height, some minor work maybe required to get correct fall etc.
The pool is formed up from the ground by 200mm so no formwork is required against this or the house, just in the areas where its shown on the drawings.
Access to the backyard is approx. 15m from the street in a straight line, barrow and pump access is fine but no way for a concrete truck to get all the way back.
100mm thick slab but may consider 75mm based on your advice. There is fall required to two small 300x300 drain points.
Concrete paths
5 concrete paths. Not sure of lenghts
Grind curve in driveway
grind curve in driveway
Repair crackes and resurface concrete around swimming pool.
Due to the heavy rain recently, the existing cracks aroud out swimming pool...
Relocation of water meter service and driveway concreting
I have an existing driveway that needs resurfacing with a small extension and...