Install cement sheeting and water proof shower area.
Install wet area panelling and shower assembly to manufacturer specifications.
Install shower base (900 x 900) and screen.
Install shelf in shower
Install towel rack
Install floating vanity.
Hang mirror above floating vanity
Tile 2 x courses above vanity
Silicone and seal all.
Plumber will be doing the fit off.
All materials supplied labour only. Approx 2 days work.